2024-04-05 -Land of the Free
|
US Navy ship programs face years-long delays amid labor, supply woes
|
[DefenseNews] Several of the U.S. Navy’s top shipbuilding programs are running one year to three years behind schedule, as the service and the industrial base grapple with workforce and management challenges.
Navy leaders conducted a 45-day review of its shipbuilding portfolio, following news in January that a first-of-class guided-missile frigate was behind schedule due in part to a workforce shortage at Fincantieri’s Marinette Marine shipyard in Wisconsin.
Coupled with existing delays to the Virginia-class attack submarine construction line and worries those delays might spill over to the top-priority Columbia-class ballistic missile submarine, Navy Secretary Carlos Del Toro that month ordered an “assessment of national and local causes of shipbuilding challenges, as well as recommended actions for achieving a healthier U.S. shipbuilding industrial base that provides combat capabilities that our warfighters need, on a schedule that is relevant.”
A SNAPSHOT OF DELAYS
The review’s leaders, Navy acquisition chief Nickolas Guertin and Naval Sea Systems Command head Vice Adm. James Downey, told reporters April 2 the review provided a snapshot of shipbuilding delays and challenges.
Based on current performance, the Navy projects the first Columbia-class SSBN will deliver 12 to 16 months later than its contractual delivery date of October 2027. The submarine is built by General Dynamics’ Electric Boat and HII’s Newport News Shipbuilding.
This is particularly worrisome because the vessel is expected to deploy shortly after its post-delivery testing and training. The Navy is obligated to have 10 SSBNs ready to deploy, lurking beneath the oceans while carrying nuclear missiles. The service is counting on the lead Columbia boat to deliver in 2027 so it can go on its maiden patrol in 2031. With any delays, the Navy will dip below the requirement.
Guertin said the Navy took significant steps prior to the pandemic to reduce risk on this program and accelerate the schedule where possible.
SUPPLY ISSUES
“COVID happened. Supply chain changed. Workforce greening happened,” he said, but previous risk-reduction steps kept the pandemic impacts “as minimal as possible.” The Columbia program, the Navy’s top acquisition priority, is the least delayed of the new programs assessed in the shipbuilding review, Guertin said.
|
Posted by NoMoreBS 2024-04-05 00:00||
||
Front Page|| [11153 views ]
Top
|
Posted by Skidmark 2024-04-05 01:36||
2024-04-05 01:36||
Front Page
Top
|
Posted by MikeKozlowski 2024-04-05 06:06||
2024-04-05 06:06||
Front Page
Top
|
Posted by Procopius2k 2024-04-05 07:27||
2024-04-05 07:27||
Front Page
Top
|
Posted by Skidmark 2024-04-05 08:15||
2024-04-05 08:15||
Front Page
Top
|
Posted by Dale 2024-04-05 08:57||
2024-04-05 08:57||
Front Page
Top
|
Posted by M. Murcek 2024-04-05 09:14||
2024-04-05 09:14||
Front Page
Top
|
Posted by swksvolFF 2024-04-05 09:42||
2024-04-05 09:42||
Front Page
Top
|
Posted by Dale 2024-04-05 10:41||
2024-04-05 10:41||
Front Page
Top
|
Posted by Dale 2024-04-05 12:20||
2024-04-05 12:20||
Front Page
Top
|
|
13:50 Abu Uluque
13:44 Abu Uluque
13:41 NoMoreBS
13:39 Abu Uluque
13:36 mossomo
13:36 swksvolFF
13:32 mossomo
13:26 Frank G
13:12 Regular joe
13:12 mossomo
13:11 swksvolFF
13:08 Abu Uluque
13:00 swksvolFF
12:59 Regular joe
12:55 Skidmark
12:53 Skidmark
12:52 Abu Uluque
12:50 Abu Uluque
12:49 Skidmark
12:48 NN2N1
12:46 Skidmark
12:44 Bobby
12:43 Abu Uluque
12:41 Bobby









|